1314 Franklin Street
Location: Oakland, CA

Project Partner: Carmel Partners

Challenge: The installation of a perimeter auger cast soldier pile / lagging shoring system, site dewatering, and 400 each 18-inch diameter auger cast building support piles up to +140 feet in depth.

Overview: Condon-Johnson was contracted to install a large scope of work in a confined area with a very tight construction schedule.

Results: Condon-Johnson was able to successfully complete this project ahead of schedule by maintaining a positive working relationship with our project partner and utilizing our key people with the right equipment.